In Letovo ground construction of the insulated transition from the dorms to the school began
The construction of the insulated transition from the Dorm to the school began. It is parallel with the completion of the finishing works on the campus of the international school "Letovo".
11 May 2017
The mounting of the fencing community "Letovo" completed
The device works on the upper and lower layers of roofing carpet underway.
18 Apr 2017
The second floor of the hostel of the school "Letovo" built
Construction of the second floor, installation of ceiling and roof in the housing 2B of the international school "Letovo" is completed, is masonry interior walls of the dormitory.
04 Mar 2017
Construction began on the 2 floor of the hostel building
Completed construction of first floor building of a hostel with an underground passage to the international school "Letovo".
14 Nov 2016
Completed a zero cycle of building of a hostel of the school
The company "Memphis" has completed the construction of a zero cycle for students. Work completed ahead of schedule.
26 Sep 2016
Began the construction of a zero cycle of a dormitory of the International school
Memfis has begun construction of a zero cycle constructions for students of the International school "Letovo".
13 Sep 2016
Memfis began construction of the hull 2B of the International school
Work began on the construction of a hostel for students (building 2B) of the International school "Letovo", where "Memphis" is the General contractor.
ISK Memfis will take part in the construction of the international school
ISK "Memfis" will take part in the project "international school "Letovo"as the General contractor for the construction of the hostel building for students with an underpass.