The reinforcement of the wall and the pylons of the first etchage of the kindergarten is coming to an end

04 May 2017
Works on 3-5 "petals" of the kindergarten building for reinforcing walls and pylons are performed by 90%.

Installation of the formwork of the floor slab of the first floor in the second "petal" is executed on 90%. Also on the third "petal" of the building, the formwork of the walls and pylons of the ground floor is being erected, 30% of the works are completed. The reinforcement of the floor slab of the first floor on the first "petal" began. The device is waterproofing the walls of the basement.